We are excited to share the latest progress on Fable Everton Park. Significant milestones have been achieved across various residences with the project starting to take shape.
Residences 26-30 now proudly display their completed form and finishes, with scaffolding removed. Inside, services rough-ins are complete, with interior finishes now commenced.
For residences 11-25, structural framing and roofing are complete, with 80% of the external cladding and finishes in place. Scaffolding is being dismantled, and services rough-ins are in progress, preparing for the upcoming interior finishes. The final three residences in this group are swiftly following suit.
Structural framing is advancing for residences 1-10 and 31-38, with roofing and cladding trades making significant headway.
Meanwhile, residences 39-42, 44, 46, 48, 56 and 57 have seen their slabs poured, with block masonry work moving forward.
Lastly, the site preparation for the private amenities is underway, with pool shell excavation and construction on the horizon.
Stay tuned for more updates as we bring the vision of Fable to life.